Australia, Sydney – Metro Western Sydney Airport: Diamond Beam Installation
750-tonne crane installs three 61-tonne diamond beams at Orchard Hills Station for Sydney Metro Western Sydney Airport project
Rail, Roads, Infrastructure
750-tonne crane installs three 61-tonne diamond beams at Orchard Hills Station for Sydney Metro Western Sydney Airport project
Multi-bridge safety enhancement across Sydenham to Bankstown line featuring complex beam installations and structural remediation
Emergency services complete comprehensive familiarization program for new metro stations, enhancing operational readiness and response capabilities
Sydney Metro project update: First tracks laid at Luddenham.
Project Launch: Sydney Metro – Western Sydney Airport Rhomberg Sersa Australia (RSA) has officially begun work on the Sydney Metro…
The Sydney Metro Southwest line has reached a significant milestone with the commencement of dynamic train testing. This marks a…
The Sydney Metro West – Eastern Tunnelling Package has reached a significant milestone with the completion of precast production. The…
Sydney Metro West – Hunter Street Station Overview A glimpse into the Sydney Metro West project. Hunter Street Station is…
High speed rail in Australia The Australian Government is planning for a future high speed rail network to connect Brisbane,…
WEBUILD JV SIGNS AU$1.7 BLN (€1 BLN) CONTRACT ON MASSIVE RAIL PROJECT IN MELBOURNE, AUSTRALIA SUBURBAN RAIL LOOP TO EXPAND…
Sydney Metro – Western Sydney Airport’s has just reached a massive milestone! The viaduct has now been constructed over the…
Hunter motorists are seeing the first glimpse of progress on the Hexham Straight Widening project with the first girder lifted…
Concessions Activity Report: August 2024 This activity report lists concessions issued during the month August 2024. For further information or…
ShoringCo, successfully completed the piling of 22 bored piles with permanent casing at Central Station, (600mm and 900mm diameters). This…
August recap. Its not all underground stations on Cross River Rail. Re-building eight stations north and south of the underground…
Tunnel boring machines (TBMs) Daphne and Beatrice are nearing the end of their journey! After breaking through at North Strathfield…
There really is PLENTY happening on Melbourne’s North East Link project. CPB Contractors team, as part of SPARK, continue to…
The double TBM breakthrough marks a milestone achievement for the Sydney Metro West – Western Tunnelling Package and the Gamuda…
Day 2 , 4 x 600 pipe culvert, magic day , brilliant effort by contractors and track assistance from the…
1st of 3 this week near Bromus on the Esperance Line of Arc network , thanks to contractors and the…
Martinus OHW team. Great work again this weekend by Martinus’s amazing team ! More info Possession PlanningPossession Planning is dedicated…
Green lights for Sydney Gateway Do you remember when those 100 metre-long, 600 tonne twin bridge spans were lifted into…
DPW Plant Hire Pty Ltd’s Ever reliable Hi-Rail SENNEBOGEN 608 equipped with it’s 1.6t 3m pin jib installing sheet piles…
Final preparations for 3 installs in 3 days this week near Norseman on Esperance Line of the Arc network More…
The T3 Bankstown Line will be closed between Sydenham to Bankstown from Saturday 24 August to Sunday 25 August 2024…
Monday 1 August 2022 to 2024 Flinders Street Station will be affected by station precinct works including the closure of…
A successful trip to the Hunter Valley for the ARTC shutdown over the weekend. 3 days worth of semi tricky…
Take a look inside Arden Station’s stunning architecture The architecture design team’s ‘loose-fit’ interior design exposes the civil engineering, making…
Busy time on the Hawkesbury River Bridge for the Sydney Trains Bridge Team. Major works have been happening to refurbish…
Final commissioning of More Trains More Services works at Waterfall, in a special nine day possession. Over the last four…
Within the station cavern (Lot 2), the team continue to progress with mechanical, electrical and ventilation service installation around the…
Construction of the Albert Street main station entrance (Lot 1) remains ongoing below and above the ground surface. Over the…
If you have any extra ordinary business deliveries or requirements our construction team needs to be aware of, we ask…
ARC Southwest track maintenance team undertook and completed the renewal of Coalfields Highway level crossing, the primary heavy haul artery…
Network closures calendar Month – Years Line Start Location End Location Service Disruption Last passenger service Track Clear Track Hand…
Albany Ring Road, new Road over Rail bridge new spans being installed today over the Arc narrow gauge network in…
Arc infrastructures Major Projects team doing a top up Ballast drop at 1 of there concrete resleepered sites north of…
Network closures calendar ID Line Service Disruption Start Location End Location Planned / Single Project Last PAX Service Track Clear…
We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.