Progress Update
- Crews poured 280,000 litres of concrete to form the foundations of the new Hopkins Road bridge.
- Two piling rings dug 48 piles.
- Road bridge embankments are under construction, with 72,000 tonnes of earth moved so far.
- The Hopkins Road level crossing will be removed.
- The new road bridge is set to open by 2026, two years ahead of schedule.