Scope of Work
-
Reballasting
-
Resleepering
-
Re-railing
Equipment Used
-
2 × DX270 excavators for scraping
-
1 × DX140 for sleeper handling
-
AR17 Personnel Carrier (due to 1-mile distance from access point)
Progress Update
✔ All work completed on schedule.
✔ Return planned for Week 10 to renew the other track.
Project Partners
-
Central Rail Systems Alliance (CRSA)
-
Quattro Plant Ltd