2. GENERAL

Work planned for the Rail Corridor must be assessed for safety and its potential to
intrude into the Danger Zone.
Work in the Danger Zone must not:
 be carried out unless there is a Safe Place that can be easily reached; and
 begin until the required safety method is in place.
Work in the Danger Zone must be carried out using one of the Protection methods
listed in this rule.
The level of safety must not be reduced:
 to allow Rail Traffic movements; or
 because of a lack of trained Workers.
A Worker in the Rail Corridor must wear approved Personal Protection Equipment
(PPE). The minimum PPE required is high visibility clothing and safety footwear.
Effective Communication with Train Controllers, Possession Protection Officers (PPOs)
and Protection Officers (POs) must be maintained.

 


Rule 3000 – PLANNING WORK IN THE RAIL CORRIDOR

1. Purpose
2. General
2.1. Accessing the Rail Corridor
3. Protection Officer
4. Assessing Safety
4.1. Use of Plant Near or Work Above the Danger Zone
5. Multiple Access Providers
6. Level Crossings
7. Methods for Working Safely on Track
7.1. Running Lines in the Network Outside Depots
7.2. In Depots
8. Local Possession Authority
9. Track Occupancy Authority
10. Absolute Signal Blocking
11. Lookout Working
12. Walking in the Danger Zone
13. Reference
14. Effective Date

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO