Rail Ops NSW Delivers Major Milestone on Main South

March Super Possession Success for ARTC

It was a huge weekend for the Rail Ops NSW team, who successfully delivered major works across the Main South lines for ARTC during the March Super Possession.

Key Achievements

Spanning three active work sites from Goondah to Frampton, the team completed:

  • 9.5 km of new rail installed

  • 19 rail defects removed, with 12 closures

  • 134 aluminothermic welds completed — zero defects

  • ✅ All scrap rail cut and stacked on site in 9m lengths

    • Included 47 leftover legs from previous rerail scopes

Ahead of Schedule, Zero Incidents

  • All works completed ahead of program

  • Delivered with zero safety incidents

  • An outstanding team effort ensuring a safe and efficient possession

👏 Massive congratulations to everyone involved for their precision, hard work, and collaboration on this critical stretch of track.


More Info

 

 

Tagged:

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Discover more from Possession Planning

Subscribe now to keep reading and get access to the full archive.

Continue reading